Kallangur, frame is up, and nobody has put the Christmas dates in the email. I know the usual story is that sites stop and come back in January. Master Builders Queensland have published their own office closures, close on 23 December, a lot of them back 4 January, some regions 11 January. That is their office. It is not a rule for my site. Page is here: Master Builders Queensland office closures.
What dates did your builder actually give you, and what still happens on site in that last week. Is it a hard stop, or do they try to hit a stage first. If you have been through a shutdown mid build before, what slipped and what was fine. I would rather a written date than a shrug in the week of the 20th.